Table 1: Timeline of events.
2009 |
|
Approval
for construction of new diagnostics building Internal
discussions on laboratory facilities specifications Building
consultants meet up |
2010 |
|
Design
planning continued |
2011 |
|
Equipment
procurement, relocation preparation Direct
CPOE label read trials |
2012 |
Apr |
Delivery
of 1st autosorter for trials, evaluation Final
design layout with workflow understandings Construction
moving towards completion |
2013 |
Jan 30 |
Building
receives construction TOP status First
delivery of Power Express (PE) Lab Automation System modules |
|
Mar 18 |
Installation
completion for PE LAS Concurrent
trials of PE LAS completed Preparation
for licencing inspection by Ministry of Health (MOH) |
|
Apr 8 |
Inspection
by MOH given in-principle approval |
|
Apr 22 |
Core
laboratories go-live |
Note-
illustrated equipment as example |